Councillor Guy Renner-Thompson
Email: guy.renner-thompson@northumberland.gov.uk
Council: Northumberland
Council Profile: View on council website
Committees:
Activity Timeline
Meetings Attended Note this may include planned future meetings.
106 meetings · Page 1 of 22
Cabinet - Tuesday, 9th December, 2025 10.00 am
The Northumberland County Council cabinet is scheduled to meet to discuss the council's financial performance, proposed changes to the council tax support scheme, and strategies for housing, education and environmental management.
Staff and Appointments Committee - Wednesday, 3rd December, 2025 2.00 pm
North Northumberland Community Partnership - Thursday, 27th November, 2025 6.00 pm
Here is a summary of the scheduled discussions for the North Northumberland Community Partnership meeting. The meeting was scheduled to include a discussion of a petition requesting a 20mph speed limit in Thropton, as well as appointments to outside bodies. Councillors were also expected to have an informal discussion session on topics including dementia care in Berwick and the Berwick Academy Build.
Health and Well-being Board - Thursday, 13th November, 2025 10.00 am
The Health and Well-being Board were scheduled to meet to discuss community mental health transformation work, receive an update on the Public Mental Health Strategy, and discuss the forward plan for future meetings. The board was also scheduled to receive an update from Citizens Advice.
Schools' Forum - Wednesday, 12th November, 2025 9.30 am
The Northumberland County Council Schools' Forum met virtually on Wednesday, 12 November 2025, to discuss several key issues impacting education in the region. These included updates on the national funding formula, a review of special educational needs (SEN) data, and a consultation on school funding. The forum was also scheduled to discuss communications from the Department for Education (DfE) and other organisations regarding special educational needs and disabilities (SEND) reforms.
Decisions from Meetings
43 decisions · Page 3 of 9
Integrated Domestic Abuse Services for Northumberland – Permission to Tender and Award Contracts
From: Cabinet - Tuesday, 14th October, 2025 10.00 am - October 14, 2025
...to procure and award contracts for an Integrated Domestic Abuse Service for Northumberland, with an initial two-year term and an option for a two-year extension, at an estimated cost of £3,488,000, authorizing the Executive Director of Children, Young People and Education and Director of Children’s Services to manage the process.
For Determination
Outline Business Case for the New School Building for Berwick Academy
From: Cabinet - Tuesday, 30th September, 2025 10.00 am - September 30, 2025
...to approve the Outline Business Case for providing new school buildings for Berwick Academy, including a revised capital funding allocation of £64.066 million and the commencement of procurement using a Design and Build strategy, with the aim of having the new school operational by September 2028.
Recommendations Approved
Summary of New Capital Proposals considered by Officer Capital Strategy Group
From: Cabinet - Wednesday, 3rd September, 2025 9.00 am - September 03, 2025
...to approve amendments to the capital programme, including funding for kitchen refurbishments at the Hartford Bridge Traveller Site, structural restoration at Woodhorn Museum, and broadband top-up vouchers, totaling several million pounds.
Recommendations Approved
Blyth Extra Care Facility
From: Cabinet - Wednesday, 3rd September, 2025 9.00 am - September 03, 2025
...to approve a capital budget of up to £10.83m from the Levelling Up Deep Dive Housing Renewal Fund for an Extra Care Facility at Delaval Terrace in Blyth, and to delegate authority for procuring a Registered Provider to build and operate the facility.
Recommendations Approved
Ashington Regeneration Programme Update
From: Cabinet - Wednesday, 3rd September, 2025 9.00 am - September 03, 2025
...to advance the Ashington Regeneration Programme, the Cabinet approved the Outline Business Case for the Portland Park Cinema and Restaurants project, delegated authority for related business case and funding approvals, authorized contracts for the Wansbeck Square redevelopment, noted progress on that redevelopment, and agreed to establish the Ashington Town Centre Highways Infrastructure project.
Recommendations Approved
Summary
Meetings Attended: 106
Average per Month: 4.6
Decisions Recorded: 43