QTR 2 FINANCE POSITION STATEMENT FOR 2023-24
November 7, 2023 Executive (Other) Approved View on council websiteFull council record
Content
Resolved –
(1) That the contents of
Document “Q” and the actions taken to manage the issues
highlighted be noted.
(2) That the following capital
expenditure schemes as outlined in
section 14.9 and 14.11 to Document “Q” be
approved:
(i)
£1.05m for city centre ducting.
This will be funded by a
mixture of current scheme budgets and £0.7m new corporate
borrowing.
(ii)
£1.4m for new equipment for
enabled care This will be funded
by new corporate borrowing.
(iii)
£0.14m for the replacement of
the rack seating at Victoria
Hall. This will be funded from the general contingency
budget.
(iv)
£0.3m for new Gym Equipment at
two Leisure Centres,
subject to final PAG approval. This will be funded by invest
to save borrowing.
(v)
£4m for the continuation of the
Empty Homes Capital
Programme. This scheme is already included in Reserve
Schemes and will be funded from capital receipts generated
by the programme.
(vi)
£0.127m for the acquisition of a
Nursery building that will be
developed as a teacher training facility. The acquisition will
be funded from the general contingency budget and the
capital development works grant funded.
(3) That
it be noted that the following has been approved under Section 1.7
of the Financial Regulations:
(i)
£2.3m for Phase 1 and
Phase 2 of the Children’s Residential homes capital scheme.
These schemes are already included in Reserve Schemes
and will be funded from corporate borrowing.
(ii)
£0.081m for the repair of
the driveway and carpark at Ingleborough
Hall. This has been funded from the general contingency
budget.
To be actioned by: Director of Finance
Overview and Scrutiny Committee: Corporate
(Andrew Cross – 01274 436823)
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 7 Nov 2023 |