CRYSTAL PALACE PARK REGENERATION PLAN - PROCEED TO PROCUREMENT FOR CAPITAL WORKS
April 18, 2024 Executive (Other) Key decision Awaiting outcome View on council websiteFull council record
Content
That
1.
Proceeding to procurement, as set out in paragraphs 3.12 to 3.26,
for a main contractor to deliver the capital works at a total
estimated contract cost of £17.7m
be approved.
2.
The budget of the Crystal Palace Park Regeneration Plan already on
the Capital Programme by £19.096m
be increased. The scheme will be funded through a
£5m grant from the National
Lottery Heritage Fund and the capital receipts from the sale of the
two areas of parkland which are estimated to achieve
£19.36m.
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 18 Apr 2024 |