CAPITAL PROGRAMME MONITORING - QUARTER 2 2024/25

November 27, 2024 Executive (Other) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to note the contents of the Capital Programme Monitoring report for Quarter 2 2024/25, including a rephasing of £11.6m, and to agree to a revised Capital Programme with several amendments, including increases for various schemes and the addition of funding for treescapes and river restoration, while also noting requests for additional funding for housing and a children's home.

Full council record
Content

That
 

1. 
The contents of the report, including a
total rephasing of £11.6m from
2024/25 and 2026/27 into future years as detailed in section 3.7,
be noted and a revised Capital Programme be agreed.

 

2. 
The following amendments to the Capital
Programme be agreed:
(i) 
Increase of £57k for the Devolved Formula Capital scheme as
detailed in paragraph 3.5.1 of the report;
(ii) 
Increase of £20k for the BMX track and associated community club
at Hoblingwell Wood Recreation Ground
as detailed in paragraph 3.5.2 of the report;
(iii) 
Increase of £26k for the Property Disposal/Feasibility Work
project as detailed in paragraph 3.5.3 of the report;
(iv) 
Increase of £8k for the Principal Road Maintenance scheme as
detailed in paragraph 3.5.4 of the report;
(v) 
Net increase of £373k for the Transport of London schemes as
detailed in paragraph 3.5.5 of the report;
(vi) 
The addition of £175k for Local Authority Treescapes Fund as
detailed in paragraph 3.8.4 of the report; and
(vii) 
The addition of £45k for The River Beck Restoration Tree Planting as
detailed in paragraph 3.8.5 of the report.
3. 
It be noted that reports elsewhere on the
agenda request the addition of £29,000k for the Bellegrove Housing Development and
£2,125k for the purchase of a new
Children’s Home.
 

Related Meeting

Executive - Wednesday 27 November 2024 7.00 pm on November 27, 2024

Supporting Documents

Capital Programme Monitoring Q2 2024-25.pdf
Appendices A to D.pdf
Appendices F G.pdf

Details

OutcomeRecommendations Approved
Decision date27 Nov 2024