Procurement Strategy for Hampden Children’s Centre Repurposing Works Delivery
May 21, 2024 Director of Property Management (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the procurement strategy for the Hampden Repurposing Works project, involving a closed tender list of five contractors evaluated on a 60/40 price/quality basis, for an estimated £541,000 over 12 weeks, and to proceed to the contract award stage.
Full council record
Purpose
This report sets out a proposed approach to the procurement of contractors to deliver the Repurposing project at Hampden Children’s Centre, NW1 1HQ. We propose to tender these works to a pre-selected list of suitably experienced tenderers using a single stage selective tendering procedure. The works to be commissioned include alterations to reconfigure the building and a variety of condition improvement works.
The tender list will be drawn up from companies in the market for these works and due diligence checks including health and safety and financial checks and pre-tender enquiries will be carried out prior to finalising the list.
The estimated contract value is £541,000.
The works are to take approximately 12 weeks with sectional completion. The works are to be procured via a closed tender process using a JCT Intermediate Building Contract with contractor’s design (ICD) 2016, with Camden amendments.
The procurement strategy report will subsequently be presented to the Director of Property Management for approval in line with Contract Standing Orders. The use of a closed tender process for a below threshold procurement complies with Contract Standing Orders (CSOs).
Decision
THAT the Director of Property Management
- Approves the procurement strategy to tender the Hampden Repurposing Works project for competitive tenders to a closed tender list of 5 contractors, using evaluation criteria of 60% price and 40% quality, for an estimated value of £541,000 over a period of 12 weeks with sectional completion.
- Agrees the project proceeds to the Contract Award stage.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 21 May 2024 |