Cardiff Heat Network - Settlement Agreement
April 10, 2025 Director of Planning, Transport & Environment (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Director of Planning, Transport & Environment approved a Settlement Agreement between Cardiff Heat Network Ltd and the Heat Network Contractor. This decision was made on 10/04/2025 to resolve contractual issues and ensure the continued delivery of the Cardiff Heat Network Project.
Full council record
Decision
The report (paragraphs 6-14) and appendices 2-4 are exempt from publication on the basis that it contains information of the description set out in paragraphs 14 and 21 of Part 4 of schedule 12 A of the Local Government Act 1972 and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information.
Appendix 1 of this report is exempt from publication on the basis that it contains information of the description set out in paragraph 16 of schedule 12A of the Local Government Act 1972.
AGREED: that consent of the Council, as sole shareholder of Cardiff Heat Network Ltd (‘CHN’), be granted to the proposed Settlement Agreement between CHN and the Heat Network Contractor (Confidential Appendix 1) to resolve issues which have arisen in relation to the contract for the delivery and operation of the Cardiff Heat Network Project.
Reasons for the decision
To approve the settlement of contractual issues which have arisen between CHN and the Heat Network Contractor in an amicable and affordable manner, ensuring the continued delivery and completion of the Heat Network Project.
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Apr 2025 |
| Effective from | 25 Apr 2025 |
| Subject to call-in | Yes |