Re:Fit 4 - Appointment of service provider to deliver Re:fit 4 Phase 1B programme of works

May 28, 2025 Director of Economic Development (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Director of Economic Development approved recommendations on 28/05/2025. The decision approved the signing of a Works Optimisation and Services agreement with Cenergist for £1,770,577.12 to deliver Phase 1B works and approved receiving an invest to save loan agreement for £1,940,577.12.

Full council record

Decision

Appendix 2 is not for publication as it contains exempt information of the description in paragraph 16 of Schedule 12A of the Local Government Act 1972

AGREED:  that

1)    the Signing of a Works Optimisation and Services agreement (WoS) with ‘Cenergist’ the Council’s appointed service provider be approved. In accordance with the Re:fit 4 call off contract procedures to deliver the works as set out in the Phase 1B Investment Grade Proposal (IGP) attached in Appendix 1.

Value of WoS = £1,770,577.12

2)    an invest to save loan agreement via the ‘Wales Funding programme SALIX energy efficiency Loan Scheme’ for the value of £1,940,577.12 with an interest rate of 2.05% repaid over 9 years be received.

Reasons for the decision

As set out in Cabinet paper ref: Refit 4 – Energy Conservation Retrofit Programme – Jan 2024, the Refit programme will deliver a number of retro fit energy conservation works packages delivering carbon, consumption and cost savings across the estate portfolio, in support of Cardiff Council’s ‘One Planet’ carbon reduction strategy.

This is the next approval stage of the Re:Fit 4 programme as outlined in the January 2024 Re:Fit 4 Cabinet Report. Phase 1A was subject to an ODR in December 2024 focussing on the installation of PV at the Council’s leisure centres.

The delivery of this Phase 1B programme as detailed in Appendix 1, will focus primarily on selected schools.

Details

OutcomeRecommendations Approved
Decision date28 May 2025
Effective from10 Jun 2025
Subject to call-inYes