Cardiff CrossRail Phase 1A - Construction Contract Award

March 19, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Cardiff Council Cabinet decided on 19/03/2026 to approve recommendations for the Cardiff CrossRail Phase 1A construction contract. Authority was delegated to the Director of Planning, Transport and Environment to finalise and award the Stage 2 Construction Contract to John Graham Construction Limited, subject to budget and funding assurances. This delegation also covers varying the Stage 1 ECI contract for costs incurred to date and enabling defined packages of works to proceed in advance of the Stage 2 Notice to Proceed.

Full council record

Purpose

CrossRail Phase 1A will be ready to start construction in 2026. The ECI Stage 1 ‘Detailed Design Phase’ is nearing completion. To move to ECI Stage 2 ‘Construction Phase’, a cabinet approval is needed due to the value of the construction contract.

Decision

Appendices 2 and 3 of this report are not for publication as they contain exempt information pursuant to the provisions of Schedule 12A Part 4 paragraph 14 of the Local Government Act 1972

RESOLVED: that

  1. Authority be delegated to the Director of Planning, Transport and Environment (in consultation with the Corporate Director for Resources and Cabinet Member for Climate Change, Strategic Planning & Transport) to finalise and award the Stage 2 Construction Contract to John Graham Construction Limited.
  2. It be noted that this delegation is conditional upon the overall project cost remaining within the approved budget and the Project Team providing assurance to the Programme Board that the project funding is adequate.
  3. authority be delegated to the Director of Planning, Transport and Environment (in consultation with the Corporate Director for Resources and Cabinet Member for Climate Change, Strategic Planning & Transport) to vary the Stage 1 ECI contract to cover all costs incurred to date, to approve any future Compensation Events under the NEC contract, and to enable defined packages of enabling works, utility diversions and site?set?up activities to proceed in advance of the Stage 2 Notice to Proceed.
  4. the risks included within the report be noted.
  5. It be noted that several elements associated with the award of this contract are commercially sensitive and are therefore provided within the confidential appendices. These include all information relating to cost, funding and programme. This information must remain confidential to protect the Council’s commercial position, and no Notice to Proceed will be issued until the conditions set out in this report and its appendices have been satisfied.

Related Meeting

Cabinet - Thursday, 19th March, 2026 10.00 am on March 19, 2026

Supporting Documents

2026-03-19 CrossRail Phase 1A.pdf
2026-03-19 CrossRail Phase 1A - Appendix 1.pdf

Details

OutcomeRecommendations Approved
Decision date19 Mar 2026
Effective from1 Apr 2026
Expected date19 Mar 2026
Originally due19 Mar 2020
Subject to call-inYes