Summary

...the conclusion of the tender award process for the Channel View regeneration project was approved, with authority delegated to relevant officers to appoint the preferred bidder and finalize contractual agreements for the project's development.

Full council record
Purpose

In March 2022 permission was
given approve the progression of the Channel View redevelopment
scheme and agree that procurement commence for a Contracting
Partner to deliver the entire project including phase 1, the design
development, consultation and planning of future phases, the
demolition of the existing
housing stock and the
construction of future phases (subject to viability).
 
The report will provide an
overview of the tender process, the outcome of the evaluation
process and identify the preferred bidder.

Content

Appendices 2a and
2b,3 and 4 are not for
publication as they contain exempt
informationofthedescriptioncontainedinparagraph 14, 16 and 21ofschedule12a of the local government act
1972.
 
Cllr Ash Lister declared a
personal and prejudicial interest in this item, left the meeting
and took no part in the decision making.
 
RESOLVED: that
 

1.           
the conclusion of the tender award process for the
Channel View regeneration project be approved.

 

2.           
Authority be delegated to the Corporate Director
People & Communities in consultation with the Cabinet MemberHousing and Communities and
Cabinet Member for Finance, Modernisation and Performance and
Director of Governance and Legal Services / Monitoring Officer and
the Section 151 Officer, to appoint the preferred bidder,
including:
 
a.        
Delegating all such
matters arising from this report required to conclude the
appointment, including matters referenced within the exempt legal
advice set out at Appendix 4;
b.        
Approve the final
contract wording and enter into the Umbrella Agreement for the
whole programme with the preferred bidder; 
c.        
Enter into a Joint
Construction Tribunal (JCT) 2016 Design & Build contract for
Phase 1 following all necessary post tender due diligence and
confirmation that the scheme is within viability
parameters;
and
d.        
Entering into
Pre-Contract Services Agreement’s (PCSA) for future
phases.
 

Supporting Documents

CAB 21 September 2023 - Channel View.pdf
CAB 21 September 2023 - Channel View - Appendix 1.pdf
CAB 21 September 2023 - Channel View - Appendix 5.pdf

Details

OutcomeFor Determination
Decision date21 Sep 2023
Subject to call-inYes