Gas Works Modular
August 8, 2023 Corporate Director of People and Communities (Officer) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to appoint Wates Construction Limited as the Main Contractor for the Gas Works Modular project, approving the entry into a JCT 2016 Design and Build Contract and a Deed of Variation to deliver 156 modular units as part of the Cardiff Living Programme.
Full council record
Content
Appendices 1, 3-6 and 8 to this report are exempt from
publication because they contain information of the kind described
in paragraphs 14, 16 and 21 of parts 4 and 5 of Schedule 12 A to
the Local Government Act 1972
AGREED
that Wates Construction Limited formally be
appointed as the Main Contractor and approval be given to enter
into a JCT 2016 Design and Build Contract (with amendments) to
build 156 Modular Units at the Former Gas Works Site, Ferry Road,
as part of the Cardiff Living Programme for a contract sum detailed
in Appendix 1. Furthermore, the Deed of Variation provided by Wates
Construction Limited be approved to formally acknowledge the
updated list of sites approved to be delivered through the Cardiff
Living programme.
Reasons for the decision
All contractual matters have
been resolved relating to the JCT form of contract and the updated
Contract Sum finalised and agreed. Therefore, we are now in a
position to enter into the formal JCT 2016 Design & Build
contract (with amendments) to progress the completion of the
development. The Deed of Variation provides the updated list of
development sites to be delivered through the Cardiff Living
programme including the Gasworks meanwhile use.
Details
| Outcome | For Determination |
| Decision date | 8 Aug 2023 |
| Subject to call-in | Yes |