Approval to Issue a second Letter of Intent (LOI) to Wates Construction Ltd for enabling & infrastructure work and elements of modular build associated with the meanwhile use of the Gasworks site.
June 21, 2023 Corporate Director of People and Communities (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Cardiff Corporate Director of People and Communities agreed on 21/06/2023 to issue a second Letter of Intent to Wates Construction Ltd. This allows Wates to continue enabling, infrastructure, and modular building works for emergency housing at the Gasworks site while finalising contract negotiations. The decision approved the issuance of the second Letter of Intent for a maximum sum identified in Appendix C.
Full council record
Decision
Appendices B, C to this report are not for publication as they contain exempt information of the description contained in paragraphs 14and 21 of Schedule 12A of the Local Government Act 1972.
AGREED: that the second Letter of Intent be issued to Wates Construction Limited for a maximum sum identified in Appendix C to continue enabling, infrastructure and modular building works for a “meanwhile” emergency housing use at the Gasworks site, whilst we conclude negotiations to enter into the JCT D&B contract covering the full scope of works
Reasons for the decision
A Letter of Intent was issued to Wates in December 2022, enabling them to begin site works and modular factory build whilst the JCT D&B contract particulars were being finalised. As Wates are now close to exceeding the value of this Letter of Intent, a second LOI is required to ensure work on site is not paused whilst the contract particulars and contract sum is being finalised and signed off.
Details
| Outcome | Recommendations Approved |
| Decision date | 21 Jun 2023 |
| Effective from | 8 Jul 2023 |