Approval To Select Contractor In Respect Of Capital Works Contract For National Lottery Heritage Fund (Nlhf) Flat Holm: A Walk Through Time Project
May 20, 2024 Director of Economic Development (Officer) Key decision Approved View on council websiteFull council record
Content
Appendix 1 to this report is exempt from disclosure
as it contains information pursuant to paragraph 16 of the Local
Government Act 1972
AGREED: that
1)
Following a procurement process, Knox and Wells be
selected as the proposed contractor to proceed to the second stage
(develop the cost plan, the approach to work packages and a
specific approach) for capital works in respect of schemes which
form an overall part of the project.
2)
Subject to the final costs being within budget, the
Council be authorised to enter into a works contract with Knox and
Wells as and when required and as detailed in the
report.
Reasons for the decision
To ensure progression of the
NLHF capital works, in line with Council procurement rules, in
order to progress the delivery of the Flat Holm NLHF work packages
and ensure completion before 1 July 2025, in accordance with grant
conditions.
Details
| Outcome | Recommendations Approved |
| Decision date | 20 May 2024 |
| Subject to call-in | Yes |