Education Sufficiency Projects- St Teilo's additional accommodation
March 31, 2023 Director of Education and Lifelong Learning (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Director of Education and Lifelong Learning approved recommendations on 31/03/2023. Approval was given to direct award the contract for St Teilo's Portacabin Ltd in the sum of £832,177, with a total project budget of £1,067,006. The Schools Programme Director was authorised to approve spend over the contract sum and within the approved budget sum.
Full council record
Decision
Education Sufficiency Projects- St Teilo’s additional accommodation
Appendix 1 to this report is exempt from publication on the basis that it contains information of the description set out in paragraphs 14 and 21 of Part 4 of schedule 12 A of the Local Government Act 1972 and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information
Appendix 2 to this report is exempt from publication on the basis that it contains information of the description set out in paragraph 16 of Schedule 12 A of the Local Government Act 1972.
Agreed: that
· approval be given to direct award the contract for the provision of permanent accommodation for St Teilo’s Portacabin Ltd in the sum of £832,177
· the total project budget of £1,067,006 be agreed which includes a sum for risk allowance of £234,829
· the Schools Programme Director be authorised to approve spend over the contract sum and within the approved budget sum
Details
| Outcome | Recommendations Approved |
| Decision date | 31 Mar 2023 |
| Effective from | 15 Apr 2023 |
| Subject to call-in | Yes |