Education Sufficiency Projects- Corpus Christi Changing block

March 31, 2023 Director of Education and Lifelong Learning (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Director of Education and Lifelong Learning approved recommendations on 31/03/2023. The decision was to direct award the contract for changing room accommodation to Portacabin Ltd for £998,336 and agree a total project budget of £1,301,996. The Schools Programme Director was authorised to approve spend over the contract sum and within the budget.

Full council record

Decision

Appendix 1 to this report is exempt from publication on the basis that it contains information of the description set out in paragraphs 14 and 21 of Part 4 of schedule 12 A of the Local Government Act 1972 and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information

Agreed: that

·      Approval be given to direct award the contract for the provision of changing room accommodation for Corpus Christi to Portacabin Ltd in the sum of £998,336

·      the total project budget of £1,301,996 be agreed which includes a sum for risk allowance of £303,660

·      the Schools Programme Director be authorised to approve spend over the contract sum and within the approved budget sum

Reasons for the decision

To enable the provision of changing room accommodation that has been displaced

Details

OutcomeRecommendations Approved
Decision date31 Mar 2023
Effective from15 Apr 2023
Subject to call-inYes