This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Cabinet of Cardiff Council decided on 19/03/2026 to approve the updated Full Business Case for the new Core Office building. Authority was delegated to the Director of Economic Development, in consultation with the Cabinet Member for Investment & Development, the Legal Officer, and the Section 151 Officer, to enter into a Development Agreement for the building, an Agreement for Lease with Wales Millennium Centre for the Capella Production Studio, manage interface works, and develop final plans for the CAT B fit-out.
Full council record
Decision
Appendices 1-6 of this report are not for publication as they contain exempt information of the description contained in paragraphs 14 and 16 of Part 4 of Schedule 12A of the Local Government Act 1972. In all circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information.
RESOLVED: that
1) the updated Full Business Case which includes the financial envelope and contingencies for delivery of the new Core Office building based on final fixed costs provided through the procurement process and the PCSA stage as set out at Confidential Appendix 2 be approved.
2) Authority be delegated to the Director of Economic Development in consultation the Cabinet Member for Investment & Development, the Legal Officer and the Section 151 Officer to:
(i) Enter a Development Agreement with the successful bidder for delivery of the new Core Office building in accordance with the draft contract set out at Confidential Appendix 5 and within the financial envelope set out at Confidential Appendix 2.
(ii) Enter into an Agreement for Lease with the Wales Millenium Centre to enable the delivery of the Capella Production Studio in accordance with the terms set out at Confidential Appendix 3 and, if required, dispose of the asset prior to practical completion
(iii) Manage budgets and appointments relating to the interface works between the Arena and Area A as set out at Confidential Appendix 2.
(iv) Develop final plans for the CAT B fit-out of the new Core Office building including Furniture, Fittings and Equipment (FF&E), ICT infrastructure, the ARC and UTCC infrastructure as set-out at Confidential Appendix 2 in-line with the capped financial envelope set out at Confidential Appendix 2 and to return to Cabinet for final consideration and approval.
Related Meeting
Cabinet - Thursday, 19th March, 2026 10.00 am on March 19, 2026
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Mar 2026 |
| Effective from | 1 Apr 2026 |
| Subject to call-in | Yes |