PMI General Building Works Contract Extension
March 24, 2025 Corporate Director of Housing (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the second permitted contract extension with Mulalley and Company Ltd for planned maintenance and improvement general building works until March 31, 2027, at an annual value of £6.5m.
Full council record
Purpose
The report aims at recommending
an extension to the current General Build Works Contract (GBW)
delivering planned maintenance programme of Kitchen and Bathroom
upgrades and refurbishments, Street roofs, MAU and Communal
flooring. •The GBW contract was let on the 1st April 2016 for
14 years (5+3+3+3), following a compliant competitive procurement
exercise. •The contract was awarded at a total contract value
range of £160m - £210m, with an annual value of
£10m - £12m maximum. •The Council has the option
of no-fault termination clause of 12 months and 18 months from the
contractor perspective. •This is a second extension as an
initial extension of 3 years is due to expire 31st March
2024.
Content
For the
reasons as detailed in the report, the Corporate Director for Housing AGREED to:
Approve the exercise of the
remainder of the second permitted contract extension option for the
delivery of Planned Maintenance and Improvement General Building
Works contract with Mulalley and
Company Ltd until 31st March 2027 at an annual value of
£6.5m. The anticipated contract budget
for the extension period is £19.5m. and the
maximum total contract value at award was £210m, therefore
spend remains within the original envelope.