Regina Road Project - Selection of Delivery Model - Part A
October 25, 2023 Approved View on council websiteFull council record
Content
RESOLVED:
1.1.
To consider delivery options and agree a direct
delivery by the Council of:
1.1.2
Phase 1, comprising an
estimated 86 new Council homes at Regina Road (minimum of 78
replacement social rent and up to 8 leaseholder/freeholder
replacements) and an estimated 8 new social rent homes at Malton
House, to the estimated household sizes set out in the report. This
delivery option enables the rebuilding of the social housing as
soon as practicable; and
1.1.3
Phase 2, comprising an
estimated 139 new Council homes (122 social rent and up to 17
leaseholder/freeholder replacements) to the housing needs of
local residents, and a replacement
onsite kindergarten/community facility. The detail of the Phase 2
option would then be reviewed and agreed by Cabinet early in 2024
before moving forward with Phase 2.
1.2.
To note that the procurement of a main contractor
will be progressed in line with delegations set out in the Annual
Procurement Plan and will cover Phase 1 works, with the option of
Phase 2 works.
1.3.
To note that the procurement of a demolition
contractor will be progressed in line with delegations set out in
the Annual Procurement Plan and will cover the clearance works for
Phases 1, 2 & 3.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 25 Oct 2023 |
| Subject to call-in | Yes |