Notice of General Exception - Regina Road demolition - Procurement strategy
September 24, 2024 Cabinet Member for Homes (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the procurement strategy for the demolition and clearance of Regina Road tower 1 and adjacent maisonettes, including asbestos removal, via a mini-competition under the Notting Hill Genesis framework for up to 12 months.
Full council record
Purpose
Regina Road demolition -
Procurement strategy for the demolition of tower 1 – nos. 1
to 87 (Phase 1a), and two adjacent blocks of maisonettes, nos. 89
to 99 and 101 to 123 Regina Road (Phase 1b).
Content
RESOLVED
to:
2.3
The Cabinet Member for Homes is recommended by the
contracts and Commissioning Board to approve the procurement
strategy for the procurement of the Regina Road demolition and
clearance contractor, including asbestos removal, via a
mini-competition under the Notting Hill Genesis framework for a
duration of up to 12 months and with an estimated total value
stated in the Part B report. The contract period will be dependent
upon project progress.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 24 Sep 2024 |
| Subject to call-in | Yes |