Revenue and Capital Budget Monitoring 2023/24 as at Month 6
November 30, 2023 Corporate and Resources Committee (Committee) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Corporate and Resources Committee noted the forecast outturn position for the General Fund, Housing Revenue Account, Schools Budget, and Dedicated Schools Grant for 2023/24 on 30/11/2023. The committee approved the re-profiling of capital budgets, decreasing them by £78.276m in 2023/24 and increasing them by £78.276m over the next three years. They also approved capital expenditure budgets for a new Housing IT System, acquisition of 50 HRA properties, Guildhall 2 renovations, Lovelace Primary school renovations, a Household Reuse and Recycling centre project, and a virement for the 2023/24 pay award.
Full council record
Decision
RESOLVED that:
1) the forecast outturn position in respect of the General Fund for 2023/24 be noted;
2) the 2023/24 forecast outturn position on the Housing Revenue Account be noted;
3) the forecast in respect of the Schools Budget and the Dedicated Schools Grant (DSG) for 2023/24 be noted;
4) the forecast outturn position in respect of the capital programme for 2023/24 be noted;
5) The re-profiling of a number of capital budgets be approved, which has the effect of decreasing capital budgets by £78.276m in 2023/24, and increasing capital expenditure budgets by £78.276m over the three year period 2024/25-2026/27, as outlined in Annex 1 (to the report);
6) Capital expenditure budget of £1.924m be approved for the implementation of a new Housing IT System (increase from £0.691m to £2.615m; £1.049m in 2023/24 and £1.566m in 2024/25), as detailed in paragraph 51;
7) Capital expenditure budget of £25.50m be approved for the acquisition of 50 HRA properties over the 3 year period 2023/24-2025/26, as detailed in paragraphs 52-54;
8) Capital expenditure budget of £0.98m be approved for Guildhall 2 – Replacement Kitchen & Bathrooms (£0.33m in 2023/24, £0.65m in 24/25), as detailed in paragraph 10;
9) Capital expenditure budget of £0.758m be approved for Lovelace Primary school renovations in 2023/24, as detailed in paragraph 11;
10)Capital Expenditure budget of £0.372m be approved for Household Reuse and Recycling centre and Waste Transfer Station project in Villiers Road (£0.08m in 2023/24, £0.292m in 2024/25), as detailed in paragraph 12;
11)A virement to allocate out centrally held budget to service areas following final agreement of 2023/24 pay award be approved, as detailed in paragraph 7.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 30 Nov 2023 |