Burlington Junior School Expansion (including Remedial Works at Burlington Infant School)
June 29, 2023 Corporate and Resources Committee (Committee) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Corporate and Resources Committee approved recommendations on 29/06/2023. The contract for Main Construction Works was awarded to Morgan Sindall for up to 22 months at a value of £23,543,173.00, and a variation of programme costs including an additional capital budget of £13.5m was approved. The Executive Director of Place was authorised to agree final terms on price and contract.
Full council record
Decision
RESOLVED that:
1) the contract for the provision of Main Construction Works be awarded to Morgan Sindall for a contract term up to 22 months from 24 July 2023 to 31 May 2025, plus 12 months latent defect period at a total anticipated contract value of £23,543,173.00;
2) the Executive Director of Place, in consultation with the Portfolio Holders for Assets, Commissioning and Waste and Children’s Services including Education be authorised to agree final terms on price and contract terms and be satisfied that there are no material changes to the proposed solution or commercial terms set out in this report; and
3) the variation of the total value of the programme costs, including the provision of an additional capital budget allocation of £13.5m, funded by DFE Basic Need Grant, be approved.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 29 Jun 2023 |
| Effective from | 14 Jul 2023 |
| Subject to call-in | Yes |