Capital Programme Update 2023/24

October 12, 2023 Executive (Other) Key decision Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

... to approve adjustments to the 2023/24 capital programme, including budget approvals for the Oakley Vale highway adoption and the North Northamptonshire Electric Vehicle Infrastructure project, as well as a reduction to the Integrated Transport Block scheme.

Full council record
Purpose

To report any adjustments to the in-year programme

Content

RESOLVED
 
KEY DECISION
 
That the Executive:
 

i) Approved the following changes
into the capital programme:
 

a. Oakley Vale, Corby Highway Adoption - £971k –
budget approval for £971k, £495k in 2023/24,
£476k in 2024/25 which is to be funded from external funds as
part of the initial Infrastructure Agreement.

b. North Northamptonshire Electric Vehicle Infrastructure
Project (NNEVI) £2.90m - £285k in 2024/25, £810k
in 2025/26 and £1.8m in 2026/27 which is to be funded from an
external grant.

c. Integrated Transport Block 2023/24 – reduction to
existing capital scheme of £184k to align the scale of the
programme with the confirmed grant funding from the Department of
Transport.
 
 
Reasons for Recommendations:
These are set out in greater detail within section 5 of the report
but can be summarised as:
 
·      
To support the statutory delivery of school places and SEND
school places across North Northamptonshire.
·      
To meet corporate plan objectives, for instance in leading in
improving the local environment
 
Alternative Options
Considered:
 
·      
As all the schemes in this report are grant funded/S106
funded, the use of the funding is in line with the agreements, so
there are no alternative option proposed in this
report.
·      
Where individual schemes are over £500k, individual
reports are presented elsewhere on the agenda that set out the
wider options that were considered before reaching the proposed
schemes identified for grant funding.

Supporting Documents

Capital Programme Update 202324.pdf

Details

OutcomeFor Determination
Decision date12 Oct 2023