Planning Application NW/24/00486 FUL - Land area 26A Stanton Cross, Mill Road, Wellingborough - Demolition of existing building & the provision of a development comprising of 47 residential dwellings
June 25, 2025 Planning Committee (Committee) Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to grant planning permission for the demolition of an existing building and the construction of 47 residential dwellings on Land area 26A Stanton Cross, Mill Road, Wellingborough, subject to the completion of a satisfactory Section 106 legal agreement and conditions, or to refuse permission if the agreement is not in place by July 30, 2025.
Full council record
Content
RESOLVED that:
(i)
powers be delegated to the Executive Director of Place and
Economy to GRANT planning permission, subject to:
a)
the completion of a satisfactory Section 106 legal agreement
which secures:
i.
appropriate planning obligations to meet the Heads of Terms
set out in Appendix 1, Section 7.135; and
ii.
the inclusion of a review mechanism to be triggered if the
development is not commenced within 2 years of the date of the
planning decision.
b)
the conditions contained within the
report (including any amendments to
those conditions deemed
necessary);
(ii)
should a satisfactory Section 106 agreement securing
appropriate planning obligations not be in place by 30 July 2025 or
any further extension of time agreed in writing between the
applicant and the Local Planning Authority, powers be delegated to
the Executive Director of Place and Economy to REFUSE planning
permission for the following reason:
a)
In the absence of a satisfactory planning obligation, the
applicant has failed to adequately demonstrate that the
infrastructure in the form of Education provision, Library
provision, Sports provision and contribution towards Special
Protection Area mitigation directly required as a result
of this scheme will be delivered. This would be contrary to
advice in the Creating Sustainable Communities - Planning
Obligations Framework and Guidance Document (2015), Sports
Provision Developer Contributions Supplementary Planning Document
(2020), Open Space Developer Contributions Supplementary Planning
Document (2020), Upper Nene Valley Gravel Pits SPA Supplementary
Planning Document (2015) and Government guidance contained within
paragraphs 35, 56, 58 and 59 of the National Planning Policy
Framework
Related Meeting
Planning Committee - Wednesday 25th June, 2025 7.00 pm on June 25, 2025
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 25 Jun 2025 |