Licence between Northamptonshire Council and Heidelberg (Hanson Quarry Products Europe) to enable the safe replacement of NNC Ref. 3122 – White Mills Bridge.
December 1, 2025 Head of Highways Delivery (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to grant a license to North Northamptonshire Council to use land owned by Heidelberg (Hanson Quarry Products Europe) for the safe replacement of White Mills Bridge.
Full council record
Purpose
To be submitted
to
democraticservices@northnorthants.gov.uk within two working
days
(by 12 noon) of the
decision having been taken.
Record of
Delegated Decision
Decision made
by
Jonathan Pearson – Head of
Highways Delivery
Decision
Title
Licence between Northamptonshire
Council and Heidelberg (Hanson Quarry Products
Europe) to enable the safe
replacement of NNC Ref. 3122 – White Mills Bridge.
Date of
decision (same as date form signed)
01/12/2025
Key
Decision
No
Decision
Grant a Licence to allow North
Northamptonshire Council to use the land owned by Heidelberg
(Hanson
Quarry Products Europe).
Reason/s for
Decision
Kier Transportation Ltd working on
behalf of North Northamptonshire Council have requested the use of
the Heidelberg (Hanson Quarry Products
Europe) adjacent to Station
Road, Earls Barton. The land comprises concrete entrance, lockable
and a solid concrete slab area, suitable for car parking and
compound/material storage throughout the duration of the
replacement of NNC Ref. 3122 - White Mills Bridge.
Alternative
options considered and rejected
Due to the limited working width
of the site, it is not possible to safely situate the compound,
welfare, storage and office facilities within the highway boundary,
therefore the land adjacent to the North-East corner of the bridge
is nearest suitable site compound. The are to the south of the
bridge is prone to flooding and therefore unsuitable for plant
machinery/traffic.
Legal
implications
New Licence required
Financial
implications
Licence fee
Other
implications
None known
Background
papers considered
Draft Licence
Location Plan -
LA1210N-KIER-GEN-BR_3122-DR-CB-0001
Land Ownership Plan –
LA1210N-KIER-SBR-BR_3122-DR-CB-0004
Declarations/conflict of
interest?
None known
Consultation
To date, stakeholder engagement
has involved Kier Transportation Ltd, North Northamptonshire
Council, Environment Agency, Natural England, Landowners and Local
Businesses. A Kier Transportation Ltd Stakeholder Officer is
assigned to the project to assist with communications.
Exempt
Decision?
N/A
Officer/
Executive member
Jonathan Pearson / Cllr Chris
McGiffen
Signed:
Jonathan Pearson
Head of Highways
Delivery
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 1 Dec 2025 |