Pre-order of steel for the Didcot to Culham River Crossing scheme
June 2, 2026 Director of Environment & Highways (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Director of Environment & Highways approved the sealing and completion of the Parent Company Guarantee between Oxfordshire County Council and John Graham Holdings Limited on 02/06/2026. This guarantee relates to the Stage One NEC4 Engineering and Construction Short Contract for the pre-order of steel for the Didcot to Culham River Crossing scheme.
Full council record
Purpose
The works under the Engineering and Construction Short Contract have commenced. The Parent Company guarantees the performance of such works.
Decision
To seal and complete the Parent Company Guarantee between (1) OCC and (2) John Graham Holdings Limited relating to the Stage One NEC4 Engineering and Construction Short Contract for the pre-order of steel for the Didcot to Culham River Crossing scheme.
Reasons for the decision
Procurement of the steelwork for the Didcot to Culham River Crossing scheme has commenced under the Engineering and Construction Short Contract. The Engineering and Construction Short Contract provides for delivery of several ancillary contracts including this PCG.
Alternative options considered
None considered. The PCG is to be delivered under the terms of the agreement
Details
| Outcome | Recommendations Approved |
| Decision date | 2 Jun 2026 |