Pre-order of steel for the Didcot to Culham River Crossing scheme

June 2, 2026 Director of Environment & Highways (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Director of Environment & Highways approved the sealing and completion of the Parent Company Guarantee between Oxfordshire County Council and John Graham Holdings Limited on 02/06/2026. This guarantee relates to the Stage One NEC4 Engineering and Construction Short Contract for the pre-order of steel for the Didcot to Culham River Crossing scheme.

Full council record

Purpose

The works under the Engineering and Construction Short Contract have commenced. The Parent Company guarantees the performance of such works.

Decision

To seal and complete the Parent Company Guarantee between (1) OCC and (2) John Graham Holdings Limited relating to the Stage One NEC4 Engineering and Construction Short Contract for the pre-order of steel for the Didcot to Culham River Crossing scheme.

Reasons for the decision

Procurement of the steelwork for the Didcot to Culham River Crossing scheme has commenced under the Engineering and Construction Short Contract.  The Engineering and Construction Short Contract provides for delivery of several ancillary contracts including this PCG.

Alternative options considered

None considered. The PCG is to be delivered under the terms of the agreement

Details

OutcomeRecommendations Approved
Decision date2 Jun 2026