Twickenham Civic Centre De-carbonisation

April 28, 2025 Finance, Policy and Resources Committee (Committee) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to agree on the scope, space allocation, asset use, financial business case, and an additional £0.46m capital budget for the Twickenham Civic Centre de-carbonisation and improvements scheme, note the construction and phasing plan and procurement process, delegate authority to enter into a construction contract, and delegate authority to dispose of 91 Queen's Road.

Full council record
Purpose

To provide an update on the Twickenham Civic
Centre De-carbonisation programme.

Content

RESOLVED:
 
The Committee resolved to:
 
a) 
Agree the scope for the decarbonisation and improvements to the
Twickenham Civic Centre campus which will be delivered under this
scheme.
 
b) 
Agree the space allocation and asset use across the campus.
 
c) 
Note the construction and phasing plan for the scheme.
 
d) 
Note the procurement process and to delegate to the Assistant
Director for Programme Management Office (PMO) in consultation with
the Executive Director of Finance the authority to enter into the construction contract at a value of
circa £7.5m to deliver the works.
 
e) 
Agree the financial business case, including projected revenue
savings, income and capital receipts.
 
f) 
Agree additional capital budget of £0.46m in 2025/26 to add
to the existing approved budget of £8.8m (total £9.26m)
to deliver the Decarbonisation and Improvements to Twickenham Civic
Centre scheme.
 
g) 
Delegate to the Assistant Director of Valuation and Asset
Management in consultation with the Director of Finance and Head of
South London Legal Partnership to dispose of 91 Queen’s Road
once it is vacated, on the open market for not less than best
consideration and to take steps necessary to obtain vacant
possession of the same.
 
h) 
Support phasing Option 2.
 

Supporting Documents

6 Twickenham Campus public_AGCB.pdf
6 Appendix B.pdf
6 Appendix C - Phasing Options.pdf

Details

OutcomeRecommendations Approved
Decision date28 Apr 2025