SURREY INFRASTRUCTURE PLAN - PHASE 5 SCHEMES
March 26, 2024 Cabinet (Cabinet collective) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to implement the Surrey Infrastructure Plan Phase 5 projects, the Surrey Flood Alleviation Programme 2024/25 to 2025/26, and the Smallfield and Reigate Flood Alleviation scheme, all within the approved budget and subject to Capital Programme Panel approval of each scheme's business case, delegating development and delivery to the Executive Director for Environment, Infrastructure & Growth in consultation with the Cabinet Member for Property, Waste and Infrastructure.
Full council record
Content
RESOLVED:
1.
That Cabinet agree the implementation of the Surrey
Infrastructure Plan Phase 5 projects identified in this report and
set out in Appendix 1, within the approved budget envelope, subject
to the final business case for each scheme being approved by the
Capital Programme Panel.
2.
That Cabinet agree the implementation of the Surrey
Flood Alleviation Programme 2024/25 to 2025/26 as identified in
this report and set out in Appendix 4a, within the approved budget
envelope, subject to the final business case for each scheme being
approved by the Capital Programme Panel.
3.
That Cabinet agree the implementation of the
Smallfield and Reigate Flood
Alleviation scheme as identified in this report and set out in
Appendix 4b, within the approved budget envelope, subject to the
final business case for each scheme being approved by the Capital
Programme Panel.
4.
That Cabinet agree to delegate the development and delivery of the
schemes to the Executive Director for Environment, Infrastructure
& Growth, in consultation with the Cabinet Member for Property,
Waste and Infrastructure.
Reasons for Decisions:
The
recommendations will enable the continued development and delivery
of infrastructure schemes that meet a wide range of outcomes and
demonstrate deliverability and affordability. They enable the
implementation of the fifth phase of SIP schemes and the
development of a continuous pipeline of projects that require
further feasibility work. The process is intended to remain dynamic
with new schemes added to the long list as they are identified. A
continuous programme of schemes will be developed taking them from
concept through to delivery identifying suitable funding
opportunities as they progress.
(The decisions on this item can be called -in by the