Contracts Forward Plan 2023/24 - Quarter 1
July 26, 2023 Cabinet (Cabinet collective) Key decision Approved View on council websiteFull council record
Purpose
This report presents the contracts being procured during quarter
one. The report also sets out the Contracts Forward Plan at
appendix 2 to this report.
The report asks for confirmation that all contracts can proceed to
contract award after tender.
Content
DECISION:
1.
To note the contract summary at Appendix 1 to the report
2.
Authorise the appropriate Corporate Director in consultation with
the Mayor to award contracts set out in Appendix 1 following an
appropriate procurement exercise, except for the contract with
ref/title ‘St George’s Leisure Centre Rebuild –
Award of Main Contractor’;
3.
Request that the contract with ref/title ‘St George’s
Leisure Centre Rebuild – Award of Main Contractor’ is
the subject of a separate report to Cabinet at the earliest
opportunity;
4.
Authorise the Director Legal Services (Monitoring Officer), to
execute all necessary contract documents in respect of the awards
of contract referred to at resolution 2.
5.
Note the procurement forward plan 2023-2028 schedule detailed in
Appendix 2 to the report.
ACTION BY:
INTERIM CORPORATE DIRECTOR RESOURCES,
C. HOLLAND
Head of Procurement (J. Parmar)
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 26 Jul 2023 |