Copenhagen Place Scheme

September 23, 2026 Cabinet (Cabinet collective) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet decided to approve recommendations regarding the Copenhagen Place Scheme on 23/09/2026. The Cabinet delegated authority to the Corporate Director of Housing & Regeneration to appropriate the land for planning purposes and use powers to override rights to light, and to agree settlements for rights of light claims.

Full council record

Purpose

This report seeks approval for S203 powers to be applied to the Copenhagen Place scheme. The Copenhagen Place scheme involves the demolition of 23 garages to deliver 18 new affordable homes (mix of 1-, 2- and 4-bed units, including 2 wheelchair units) with associated landscaping.

Decision

 DECISION:

  1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to appropriate the Land for planning purposes in accordance with section 122 Local Government Act 1972 and subsequent use of the Council’s powers under s203 s206 of the Housing & Planning Act 2016 to override rights to light of neighbouring properties that would be infringed by the redevelopment the Land.
  2. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to agree the settlement of rights of light claims with an affected party, together with any associated fees.
  3. Delegate authority to the Director of Governance and Legal Services in consultation with the Mayor to agree the terms of and enter into any documentation required to deal with any property matters necessary to progress the development of the Land.
  4. Note that the cost of the proposed settlement of rights of light compensation payments and associated fees will be met from the capital budget for the Copenhagen Place Garage site development.

REASONS FOR DECISION:

  1. The decisions sought in this report are to enable the construction on the Land of the new building a 4-storey residential housing block.
  2. The Council has instructed Rights of Light Consultant to carry out an analysis to identify surrounding properties which may suffer an adverse impact to the level of light currently maintained. They reported that there are potentially 5 buildings that may be affected by the development with the individual dwellings therein being affected to varying degrees as detailed in the right to light report.
  3. Rights of Light Consultant have also assessed the level of light infringement to each individual property that is affected and provided details of the potential settlement budget for the release of these rights. Full details of the affected parties, settlement budgets as well as negotiations are set in the exempt appendix. Due to the high risk of an injunction to prevent the scheme being delivered and the associated settlement costs, the Council needs to consider appropriate use of its powers to mitigate these risks.

ALTERNATIVE OPTION:

Do nothing option: if the Council decides not to appropriate the Land, then there is the potential that affected private property owners could bring injunction proceedings which could stop the construction of the project or significantly delay its delivery and the18 new affordable homes.

Action by: Corporate Director of Housing and Regeneration

Related Meeting

Cabinet - Wednesday, 23rd September, 2026 3.00 p.m. on September 23, 2026

Supporting Documents

Copenhagen Place Scheme.pdf
Appendix 1 - Site Plan.pdf
Appendix. 2 for Copenhagen Place Scheme.pdf

Details

OutcomeRecommendations Approved
Decision date23 Sep 2026
Effective from3 Oct 2026
Expected date23 Sep 2026
Originally due23 Sep 2026
Lead officerHannah Dalgleish
Subject to call-inYes