Green Recovery Fund Round 2 - Strategic Pollinator Project - Change Request
June 4, 2026 Director of Operations (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Director of Operations approved changes to the Keynsham Community Energy project on 23 April 2026. This included extending project milestones to August 2026 and reprofiling £16,220 of revenue funding.
The Director of Place approved changes to the Strategic Pollinator Project on 04 June 2026. This involved reallocating £61,705 of underspend and £17,435 of budget across cost headings.
The Executive Director for Transport approved the Full Business Case for Bath City Centre Phase 2 and awarded £377,000 of CRSTS funding to Bath and North East Somerset Council on 23 April 2026.
Full council record
Decision
That the Director of Place in consultation with Environment Directors take the decision to approve:
1) Reprofile: Reallocation of project underspend through a reprofile of £61,705 from 25/26 to 26/27.
2) Cost: Reallocation of budget across agreed cost headings to the value of £17,435.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 4 Jun 2026 |