Thornbury (Grovesend/Gillingstool)

May 18, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved the reprofiling of £75,175.67 of Investment Fund spend from 2025/26 into 2026/27. The revised project milestone sets the FBC delivery date to March 2027, with construction and TRO milestones removed.

Full council record

Decision

That the Executive Director of Transport approves:

1)    The reprofiled spend of £75,175.67 of Investment Fund (IF) from 2025/26 into 2026/27.

2)    The revised project milestone sets the FBC delivery date to March 2027. Construction and TRO milestones have been removed, as they are dependent on future delivery funding and will be confirmed at the point of FBC approval.

23/24

24/25

25/26

26/27

Total

Current

£119,189

£31,370

£219,441

£500,000

£870,000

Actual/proposed

£119,189

£31,370

£144,265.33

£575,175.67

£870,000 

Difference

-

-

(75,175.67)

+£75,175.67

-

Supporting Documents

Thornbury Grovesend-Gillingstool.pdf

Details

OutcomeRecommendations Approved
Decision date18 May 2026