Active Travel Fund Extension (ATFe) Concorde Way Phase 1

April 8, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved recommendations on 08/04/2026. The project's approved capital funding increased, the construction dates were revised, the spend profile was updated, and cost headings were reduced.

Full council record

Decision

That the Executive Director of Transport approves:

  1. The increase in the project AFC from £180,398 to £230,170, and that SGC will fund the additional £49,772 required to ensure completion of the scheme.
  2. The change in the construction start date from July 2025 to July 2026, with the construction completion date correspondingly moved from December 2025 to September 2026. This revision will affect preceding milestones and ensures work is delivered during the school holiday period to minimise disruption to users.
  3. The updated spend profile, which transfers £110,140 from FY2025/26 to FY2026/27.
  4. The reduction of cost headings from eight to two, to facilitate the approval of claims.

Supporting Documents

Active Travel Fund Extension ATFe Concorde Way Phase 1.pdf

Details

OutcomeRecommendations Approved
Decision date8 Apr 2026