Active Travel Fund 3 - Kingswood Town Centre Links

May 18, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved recommendations for the Active Travel Fund 3 - Kingswood Town Centre Links scheme on 18/05/2026. The decision extended the construction completion milestone to 31 March 2026 and reprofiled £122,258 of funding into 2026/27. This included updating the forecast between cost headings, reducing contingency and increasing allocations for construction, design, and project management.

Full council record

Decision

That the Executive Director of Transport approves:

1)    The revised construction completion milestone, extending final completion from February 2026 to 31 March 2026

2)    The reprofiled spend of £122,258 of Active Travel Fund 3 funding to move from 2025/26 into 2026/27 to reflect post completion activities. 

1)    The updated forecast between cost headings, including reduction in contingency and corresponding increases in construction, design, and project management allocations. 

22/23

23/24

24/25

25/26

26/27

Total

ATF3

ATF3

ATF3

ATF3

ATF3

ATF3

Current

£26,647

£99,126

£599,282

£943,378

0

£1,668,433

Proposed

£26,647

£99,126

£599,282

£821,120

£122,258

£1,668,433

Change

(122,258)

(122,258)

Supporting Documents

Active Travel Fund 3 - Kingswood Town Centre Links.pdf

Details

OutcomeRecommendations Approved
Decision date18 May 2026