Low Carbon Challenge Fund Extension - Local Energy Scheme Change Request

April 23, 2026 Director of Operations (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Director of Operations approved changes to the Keynsham Community Energy project on 23/04/2026. The project's solar rooftop development milestones were extended by five months to the end of August 2026, and £16,220 in revenue was reprofiled from 2025/26 into 2026/27.

Full council record

Decision

That the Director of Operations in consultation with UA Environment Directors approves the following changed to the Keynsham Community Energy project which has been awarded Local Energy Scheme revenue funding, part of the Low Carbon Challenge Fund programme.

1)    Milestones: The Keynsham Community Energy Local Energy Scheme revenue project requires additional time to complete the development work of their solar rooftop projects on Keynsham Leisure Centre, moving from March to the end of Aug 26 (5 months). No additional funding is required.

2)    Financial: Reprofiling of £16,220 revenue in the Local Energy Scheme from 25/26 into 26/27.

Supporting Documents

Low Carbon Challenge Fund Extension Local Energy Scheme Change Request.pdf

Details

OutcomeRecommendations Approved
Decision date23 Apr 2026