Bristol and Bath Railway Path Full Business Case (FBC) - amendment
July 20, 2026 Chief Executive, West of England Combined Authority (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Chief Executive, West of England Combined Authority, approved amendments to the Bristol and Bath Railway Path Full Business Case on 20/07/2026. The decision approved a reduction in the CRSTS drawdown figure from £296,180 to £221,180 and included a revised spend profile.
Full council record
Decision
Decision Taken
That the West of England Mayoral Combined Authority Chief Executive Officer:
- Approves amendment of the CRSTS drawdown figure mentioned inDecision Reference Number 25_175 from £296,180 to £221,180 and the inclusion of the spend profile below to ensure further clarity.
Pre 2025/26
2025/26
2026/27
2027/28
Total
CRSTS
£207,737
£76,263
£221,180
£505,180
Economic Development Fund (CRSTS Match Funding)
£154,000
£13,000
£167,000
Total
£207,737
£76,263
£375,180
£13,000
£672,180
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 20 Jul 2026 |