CRSTS Re-baseline - Somer Valley Links and Bath Walking, Wheeling and Cycling Links
July 8, 2026 Executive Director of Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive Director of Transport approved the drawdown of £1,612,000 for the Bath Walking & Wheeling Cycling links project and £495,000 for the Somer Valley Links project. These funds are from the City Regions Sustainable Transport Settlement capital funding. The decision was made on 08/07/2026.
Full council record
Decision
That the Executive Director of Transport:
1) Approves the drawdown of £1,612,000 of City Regions Sustainable Transport Settlement (CRSTS) capital funding transferred from the delivery to the development allocation for the Bath Walking & Wheeling Cycling links project by Bath and North East Somerset Council to bring the scheme to FBC stage.
2) Approves the drawdown of £495,000 of City Regions Sustainable Transport Settlement (CRSTS) capital funding transferred from the delivery to the development allocation for the Somer Valley Links project by Bath and North East Somerset Council to bring the scheme to FBC stage.
*To note this was approved as part of the CRSTS re-baselining decision, originally published in Officer Decision Notice 25_398. Revised awards and profile shown below:
Grant Awards:
Scheme
Previous CRSTS Funding
Draw down CRSTS Funding
Current CRSTS Funding
Bath Walking Wheeling Cycle Links
900,000
1,612,000
2,512,000
Somer Valley Links
3,605,000
495,000
4,100,000
Spend Profile:
Bath Walking Wheeling & Cycle Links
Pre 25/26
25/26
26/27
Total
Current
£900,000
£900,000
Proposed
£99,000
£1,513,000
£1,612,000
Total
£900,000
£99,000
£1,513,000
£2,512,000
Somer Valley Links
Pre 25/26
25/26
26/27
Total
Current
£3,605,000
£3,605,000
Proposed
£386,000
£109,000
£495,000
Total
£3,605,000
£386,000
£109,000
£4,100,000
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 8 Jul 2026 |