Active Travel Fund 6 - Prince Street Bridge Pedestrianisation
July 2, 2026 Executive Director of Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive Director of Transport approved the revised delivery timeframe and funding reprofiling for the Prince Street Bridge Pedestrianisation scheme on 02/07/2026. The construction start date was deferred to January 2028, and £455,000 of Active Travel Fund 6 capital funding was reprofiled into 2027/28.
Full council record
Decision
That the Executive Director of Transport Approves:
1) The revised delivery timeframe, deferring the construction start date of the Prince Street Bridge Pedestrianisation scheme from February 2027 to January 2028, to align with completion of the Bedminster Bridges City Region Sustainable Transport Settlement scheme.
2) To reprofile £455,000 of Active Travel Fund 6 (ATF6) capital funding from the 2025/26–2026/27 profile into 2027/28 to reflect the updated delivery programme and deferred construction timetable as shown below:
25/26
ATF6
26/27
ATF6
27/28
ATF6
Total ATF6
Current
£5,000
£520,000
£75,000
£600,000
Proposed
£0
£70,000
£530,000
£600,000
Change(+/-)
-£5,000
-£450,000
+£455,000
-
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 2 Jul 2026 |