Active Travel Fund 6 - Prince Street Bridge Pedestrianisation

July 2, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved the revised delivery timeframe and funding reprofiling for the Prince Street Bridge Pedestrianisation scheme on 02/07/2026. The construction start date was deferred to January 2028, and £455,000 of Active Travel Fund 6 capital funding was reprofiled into 2027/28.

Full council record

Decision

That the Executive Director of Transport Approves:

1)     The revised delivery timeframe, deferring the construction start date of the Prince Street Bridge Pedestrianisation scheme from February 2027 to January 2028, to align with completion of the Bedminster Bridges City Region Sustainable Transport Settlement  scheme.

2)     To reprofile £455,000 of Active Travel Fund 6 (ATF6) capital funding from the  2025/26–2026/27 profile into 2027/28 to reflect the updated delivery programme and deferred construction timetable as shown below:

25/26

ATF6

26/27

ATF6

27/28

ATF6

Total  ATF6

Current

£5,000

£520,000

£75,000

£600,000

Proposed

£0

£70,000

£530,000

£600,000

Change(+/-)

-£5,000

-£450,000

+£455,000

-

Supporting Documents

Active Travel Fund 6 Prince Street Bridge Pedestrianisation.pdf

Details

OutcomeRecommendations Approved
Decision date2 Jul 2026