Somer Valley Links Programme - Phase 3 - Bear Flat Early Works Funding Application

June 26, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved the Somer Valley Links Programme - Phase 3 - Bear Flat Early Works Funding Application on 25/06/2026. This decision approves the draw down of £1,203,538 of CRSTS capital funding by Bath and North-East Somerset Council for early works. This approval is conditional on the reallocation of CRSTS funds to ensure the project is fully funded.

Full council record

Decision

That the Executive Director of Transport:

1)     Approves the Early Funding Works Application for the Bear Flat section of the Somer Valley Links – Phase 3 project.

2)     Approves the draw down of £1,203,538 of City Regions Sustainable Transport Settlement (CRSTS) capital funding by Bath and North-East Somerset Council to complete the delivery of the early works, to be profiled within 26/27.

Profile

25/26

26/27

27/28

Total

Proposed Drawdown

£1,203,538

£1,203,538

This approval is conditional on the approval of the reallocation of CRSTS funds to the Somer Valley Phase 3 work-package to ensure the project is fully funded with CRSTS.

Supporting Documents

Somer Valley Links Programme_Phase 3_Bear Flat_July 2026_Executive Director of Transport 002.pdf

Details

OutcomeRecommendations Approved
Decision date26 Jun 2026