Metrowest Phase 2 - DSA ES4-Refresh - Variation 1

July 8, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport awarded Network Rail a contract variation. This variation was approved on 08/07/2026 to the Development Services Agreement for North Filton and Henbury stations. The variation adds £677,364.93 to the contract, bringing the revised total to £3,604,613.93.

Full council record

Decision

That:

Network Rail are awarded a contract variation to the original Engineering Stage 4 (ES4) Refresh Development Services Agreement (DSA) for North Filton and Henbury stations.

The value of the variation is £677,364.93, representing 25.34% of the original contract value. The revised contract value is £3,604,613.93.

Supporting Documents

121 MetroWest Phase 2_DSA_ES4 Refresh_Variation 1_July 2026_Executive Director of Transport.pdf

Details

OutcomeRecommendations Approved
Decision date8 Jul 2026