The Executive Director of Transport approved the Bedminster Bridges Full Business Case and combined it with the Redcliffe Roundabout project. This decision, made on 27/07/2026, approves £12,749,531 in grant funding for Bedminster Bridges and amends the Redcliffe Roundabout award. The decision also approves the amalgamation of grant awards to facilitate a singular build contract with a construction start date of November 2026 and an end date of May 2028.

Full council record

Decision

That the Executive Director for Transport:

1)     Approves the Full Business Case (FBC) for Bedminster Bridges.

2)     Approves the combination of Bedminster Bridges and Redcliffe Roundabout projects into a single project with construction start date of November 2026 and end date of May 2028.

3)     Approves the award of £12,749,531 of City Region Sustainable Transport Settlement (CRSTS BE) capital funding to Bristol City Council for construction and delivery of Bedminster Bridges as detailed in the FBC.

4)     Approves the amendment of the existing Redcliffe Roundabout award (CRSTS BR) to include a) £5,395 CRSTS, bringing the CRSTS BR award total to £5,381,491.

5)     Approves the amalgamation of the Redcliffe Roundabout and Bedminster Bridges grant awards to facilitate the letting of a singular build contract.

a.     This brings the overall total for CRSTS BR to £18,131,022 CRSTS plus £600,000 Economic Development Fund and an additional £44,974 local contribution.

6)     Notes that £64,964 early works funding and £736,708 development has previously been awarded under CRSTS BE, of which £190,462 remains to be spent in FY 26/27, and approves the future funding profile for the combined projects as below.

Current allocations

Redcliffe Roundabout

£6,026,465

Bedminster Bridges

£13,608,280

Total

£19,634,745

Allocation breakdown – Bedminster Bridges and Redcliffe Roundabout

Redcliffe Roundabout (CRSTS BR) – CRSTS

£5,381,491

Redcliffe Roundabout (CRSTS BR) – EDF

£600,000

Bedminster Bridges (CRSTS BE) - CRSTS

£13,551,202

Local Contribution (Redcliffe Roundabout)

£44,974

Local Contribution (Bedminster Bridges)

£57,078

Total

£19,634,745

Current grant awards

Total

Redcliffe Roundabout (CRSTS BR) – CRSTS

£5,376,096

Redcliffe Roundabout (CRSTS BR) – EDF

£600,000

Bedminster Bridges (CRSTS BE) – CRSTS

£736,708

Bedminster Bridges early works

£64,964

Total

£6,777,768

Proposed additional grant awards

Total

Redcliffe Roundabout (CRSTS BR) – CRSTS

£5,395

Bedminster Bridges (CRSTS BE) – CRSTS

£12,749,531

Total

£12,754,926

Spend profile of combined Bedminster Bridges and Redcliffeprojects

Financial year

CRSTS (BE/BR)

EDF/Local Contribution

Total

Prior to 26

£608,419

£0

£608,419

2026/27

£2,587,536

£0

£2,587,536

2027/28

£12,396,183

£494,062

£12,890,245

2028/29

£3,340,555

£207,990

£3,548,545

Total

£18,932,694

£702,052

£19,634,745