Lawrence Hill Step Free Access Scheme - Approval of Additional Funding Allocation and Reallocation of CRSTS Funding

August 6, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved the revised programme baseline for the Lawrence Hill Step Free Access Scheme, with completion now planned for September 2027. This decision also approved additional project funding of £1,019,950 and the reallocation of £1,019,950 City Regions Sustainable Transport Settlement capital funding from another project. The decision was made on 06/08/2026.

Full council record

Decision

That The Executive Director of Transport

1)             Approves the revised programme baseline for the Lawrence Hill Step Free Access Scheme, with completion now planned for September 2027.

2)             Approves the additional project funding of £1,019,950 to enable completion of the remaining detailed design and construction works.

3)             Approves the reallocation of £1,019,950 City Regions Sustainable Transport Settlement capital Funding from the Bristol to Bath Strategic Corridor (BBSC) Bristol Phase 2 project to the Lawrence Hill Step Free Access Scheme within the MCA's CRSTS programme as profiled below

BBSC BCC Phase 2 Funding Profile:

Funding Stream

Pre 26/27

26/27

27/28

28/29

Total

BBSC - BCC P2 (Current)

£830,450

£1,443,488

£1,387,150

£338,912

£4,000,000

BBSC - BCC P2 (Proposed)

£830,450

£1,351,727

£797,873

£2,980,050

Lawrence Hill Step Free Access Funding Profile:

Funding Stream

Pre 26/27

26/27

27/28

28/29

Total

IF Revenue

£41,000

£41,000

TCF

£136,322

£136,322

CRSTS

£3,038,555

£3,557,829

£6,596,384

£6,773,706

Funding Stream

Pre 26/27

26/27

27/28

28/29

Total

IF Revenue

£41,000

£41,000

TCF

£136,322

£136,322

CRSTS

£2,376,219

£4,462,827

£752,288

£25,000

£7,616,334

£7,793,656

Supporting Documents

Lawrence Hill Step Free Access Scheme Approval of Additional Funding Allocation and Reallocation o.pdf

Details

OutcomeRecommendations Approved
Decision date6 Aug 2026