M32 Sustainable Transport Corridor
July 8, 2026 Executive Director of Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive Director of Transport approved the draw down of £1.69m of funding to continue work on the Outline Business Case for the M32 Sustainable Transport Corridor on 08/07/2026. This decision involved agreeing to a series of Executive Director meetings and noting financial implications. The funding movement shifts budget allocated for the Full Business Case to cover ongoing Outline Business Case development.
Full council record
Decision
That the Executive Director for Transport
- Approves the draw down £1.69m (including risk and contingency) of City Regions Sustainable Transport Settlement (CRSTS) capital funding from the existing Full Business Case allocation to continue working on the Outline Business Case as shown in the table below:
Proposed
Up to 25/26
26/27
27/28
Total
OBC
£4,191,605
£1,396,074
£5,587,679
FBC
£320,567
£4,871,361
£5,191,928
- Agrees to a series of Executive Director meetings to establish alignment on programme extents and how best to deliver wider corridor aspirations.
- Notes the financial implications of this change; moving budget allocated for the FBC to cover the ongoing OBC development as set out below.
Total grant amount (CRSTS)
Grant
CRSTS
OBC
CRSTS
FBC
Current
£4.23m
£6.55m
£10.78m
Proposed
£5.59m
£5.19m
£10.78m
Movement
+£1.36m
-£1.36m
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 8 Jul 2026 |