Variation to MetroWest Phase 2 - Henbury ES5 DevelopmentServices Agreement (DSA)

October 9, 2026 Director of Finance, Investments and Commercial (S.73 Officer) (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Director of Finance, Investments and Commercial and the Chief Executive of West of England Combined Authority approved a contract variation on 09/10/2026. Network Rail was awarded a contract variation of £477,059.51 to the Henbury Development Services Agreement (DSA) ES5, increasing the new contract value to £7,241,439.24. This variation covers additional design and development activities for enhanced infrastructure and pedestrian/cycle ramp costs.

Full council record

Decision

That the Chief Executive and S73 or MO approves:

1) That Network Rail are awarded a contract variation to the original Henbury Development Services Agreement (DSA) ES5.

The total original contracted price is £6,764,379.72 The variation is for £477,059.51 (7%)

New Contract Value is £7,241,439.24

Supporting Documents

154 26_339_ODN_VariationToMetrowestPhase2_unisgned.pdf

Details

OutcomeRecommendations Approved
Decision date9 Oct 2026