Network Rail - Metrowest 2 - North Filton - DSA - ES5 - Detailed Design - Variation 1

July 10, 2026 Director of Finance, Investments and Commercial (S.73 Officer) (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Director of Finance, Investments and Commercial (S.73 Officer) approved a contract variation for Network Rail for the North Filton station's Engineering Stage 5 Detailed Design on 10/07/2026. The variation reduces the contract value by £742,809.20 to £4,123,793.80. This formalises the removal of signalling scope and captures additional design activities for project progression.

Full council record

Decision

That:

1) Network Rail are awarded a contract variation to the original Engineering Stage 5 (ES5) Development Services Agreement (DSA) for North Filton station.

The total original contracted price is £ 4,866,603. The variation is for -£ 742,809.20 (- 15.3%)

New Contract Value is £ 4,123,793.80

Supporting Documents

155 2026-11-03_NR-NF-DSA-ES5-Design-Variation 1-ODNAmended-SR_unsigned.pdf

Details

OutcomeRecommendations Approved
Decision date10 Jul 2026