Content: RESOLVED that: 1. approval be given to proceed with the development of the RIBA Stage 2 design presented in this report for the redevelopment of the Household Reuse and Recycling Centre and Waste Transfer Station be progressed to RIBA Stage 4 (i.e. technical design); 2. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder and the Commissioning Governance Board to finalise the details of the procurement strategy as outlined in paragraphs 11 to 17 and to enter in contract as required for the delivery of the project up to the end of RIBA Stage 4; and 3. approval be given for the submission of a planning application.
Supporting Documents
Related Meeting
Licensing Sub-Committee - Tuesday 26 August 2025 9:45 am on August 26, 2025