Audit and Performance Committee - Thursday 22nd October, 2026 6.30 pm
October 22, 2026 at 6:30 pm Audit and Performance Committee View on council website Watch video of meetingSummary
Open Council Network is an independent organisation. We report on Westminster and are not the council. About us
The Audit and Performance Committee of Westminster Council reviewed the council's audited accounts for 2025/26, receiving an unmodified opinion from external auditors Grant Thornton. The committee also noted the positive value-for-money assessment from Grant Thornton, which identified no significant weaknesses in the council's arrangements for financial sustainability, governance, or economy, efficiency, and effectiveness.
Annual Complaints Report
The committee received the Annual Complaints Report for 2025/26, which detailed a 19% increase in Stage 1 complaints to 2,887, while Stage 2 complaints decreased by 13% to 639. Response times were impacted by a cyber incident in November 2025, leading to 71% of Stage 1 and 60% of Stage 2 corporate complaints being responded to within target. The Local Government and Social Care Ombudsman (LGSCO) investigated 19 complaints, upholding 18, with the council achieving 100% compliance with recommended remedies. Housing Services accounted for 72% of all complaints. Priorities for 2026/27 include implementing a new complaints system in Microsoft Dynamics and increasing the use of AI to support complaint handling.
Audited Accounts and Audit Findings Report (Council)
The committee reviewed the Audited Accounts and Audit Findings Report for the council for 2025/26. Grant Thornton reported that the audit was substantially complete and an unmodified opinion was expected. The audit had been complex due to accounting treatments for temporary accommodation partnerships and additional cyber assurance work. Key adjustments related to phased A2Dominion sales, agency versus principal roles, sale-and-leaseback accounting, disposal judgements, right-of-use assets, lease liabilities, and capital receipts. These were noted as technical adjustments that did not alter the General Fund outturn. The committee noted that additional audit fees had arisen due to the extra work required for these transactions and the cyber incident, and these were not expected to recur at the same level. The committee noted the expected unmodified opinion and approved the adjustments reflected in the final audited accounts, delegating residual matters to the Section 151 Officer. A post-audit review was agreed to identify lessons for managing complex transactions.
Audited Accounts and Audit Findings Report (Pension Fund)
The committee received a summary of the Audited Accounts and Audit Findings Report for the Pension Fund. The Fund was valued at approximately £2.2 billion and remained strongly funded. The audit progressed smoothly, with an unmodified opinion expected and no adjusted or unadjusted financial statement misstatements identified. The committee welcomed the positive working relationship between the council and external auditors, and noted that pension payments and investment operations continued without interruption during the cyber incident. The report highlighted an 8% increase in active membership, likely due to backlog clearance and workforce growth. The committee requested clarification on the wording regarding currency risk mitigation, noting that the Fund held a hedged share class within a passive fund rather than undertaking direct foreign exchange hedging. The committee approved the 2025/26 Pension Fund Statement of Accounts and noted the Audit Findings Report. It was agreed that the wording on currency hedging would be clarified.
External Auditor's Annual Report
The committee received the External Auditor's Annual Report from Grant Thornton, which assessed the council's value-for-money arrangements. Grant Thornton found no significant weaknesses in the council's value-for-money arrangements and provided positive assessments of financial sustainability, governance, and arrangements for improving economy, efficiency, and effectiveness. The report noted that the council's financial position was less comfortable than in previous years, with difficult medium-term decisions ahead, but that proposed actions were considered capable of addressing the risk. The emerging Dedicated Schools Grant deficit was highlighted as a national issue requiring continued attention. The committee noted Grant Thornton's Value for Money assessment and welcomed that no significant weaknesses or improvement recommendations had been identified.